Project Overview
CEG was selected to supply a range of air distribution products for the Whitecraig Primary School project on behalf of OCS.
Working closely with the project team, we supplied a package of high quality ventilation products manufactured by RCM Products, helping to provide effective air distribution throughout the school while meeting the project’s performance and aesthetic requirements.
The solution included Adjustable Swirl Diffusers, Louvre Faced Diffusers and Fixed Blade Louvres, all selected to suit the specific needs of the various teaching and communal spaces within the building.
Main Challenge
As with many education projects, maintaining programme deadlines was critical to ensure the building could be completed and occupied on schedule.
The project also required careful coordination of product selections to ensure airflow performance, appearance and installation requirements were all met without compromising delivery timescales.
Solution Provided
CEG worked closely with OCS and RCM Products throughout the project to provide technical support, product selection assistance and reliable supply of the specified equipment.
Our team coordinated the supply of:
• Adjustable Swirl Diffusers for efficient and flexible air distribution
• Louvre Faced Diffusers to provide effective ventilation while maintaining architectural appearance
• Fixed Blade Louvres for robust and reliable air transfer applications
By maintaining close communication with all parties, we ensured products were manufactured, delivered and supplied in line with the agreed project programme.
Result
The project was successfully completed with all ventilation products delivered within the required timescales.
CEG’s technical support and supply chain management helped ensure a smooth installation process, allowing OCS to maintain programme commitments and deliver the project successfully.
The completed installation provides effective air distribution throughout the school, supporting a comfortable and healthy learning environment for pupils and staff.
Thistle Centre
View the work we carried out for Thistle Centre
The Macallan Distillery
View the work we carried out for The Macallan Distillery
Old Course Hotel & Pro Shop, St Andrews
View the work we carried out for Old Course Hotel & Pro Shop, St Andrews
M&S Weymouth Case Study
View the work we carried out for M&S Weymouth Case Study
Equinix Data Centre
View the work we carried out for Equinix Data Centre
Dalmilling Primary School Case Study
View the work we carried out for Dalmilling Primary School Case Study
Ready to Work with CEG?
We’re here to help you find the perfect HVAC solution. Discuss your project by filling out our form, giving us a call, sending us an email or popping in at our Glasgow office.